$1.8 billion Sydney Metro contract awarded to CPB Contractors and Ghella

Major works are set to commence on the new Sydney Metro – Western Sydney Airport metro line after a $1.8 billion contract was awarded to CPB Contractors and Ghella to build the new twin metro rail tunnels in late December.
The driverless 23-kilometre metro line will link St Marys to the centre of the new Aerotropolis via the new Western Sydney International (Nancy-Bird Walton) Airport, with six stations to be built along the alignment.
The 9.8 kilometres of twin rail tunnels will be delivered in two sections. The 4.3-kilometre northern tunnels run from St Marys to Orchard Hills and the 5.5-kilometre southern section of tunnels runs between the Airport Business Park and the Aerotropolis Station;
Apart from the twin tunnel, the Station Boxes and Tunnelling contract includes excavation and civil works for new stations at St Marys, Orchard Hills, Western Sydney International (Nancy-Bird Walton) Airport, and Aerotropolis.
CPB Contractors and Ghella will build one of the two temporary precast concrete factories for the project on the Western Sydney International site, which will produce more than 67,000 concrete segments to line the twin tunnels. The teams will also build two TBM launch sites at Orchard Hills and Western Sydney International and two TBM retrieval sites at St Marys and Aerotropolis Station.